Patience Tarhemba
A fresh inspection of the redeveloped Obalende Y’ello Bus Park has confirmed that the Lagos State Government now expects the facility to be ready for public use by the end of December 2026.
Making the disclosure on Friday, November 20, the Commissioner for the Environment and Water Resources, Tokunbo Wahab, announced the revised completion target during a tour of the site being developed with support from telecommunications giant MTN Nigeria.
The transport facility is built to ease congestion and bring order to one of Lagos Island’s busiest transport corridors, the facility is designed to accommodate approximately 1,000 buses while transforming the Obalende under bridge environment into a cleaner, more organised transport hub.
Wahab explained that the project, which was initially scheduled for completion within 21 weeks, encountered delays arising from operational and logistical challenges involving transport operators already conducting business at the location.
Resolving the bottlenecks required bringing all the key players to the table, with the government engaging transport unions, contractors and the Special Adviser to the Governor on Transportation, Sola Giwa, to clear the way for construction to continue.
Out of those talks came a temporary arrangement, under which existing operators agreed to vacate the immediate construction area for a maximum of six weeks without completely shutting down their activities.
That window, according to the commissioner, is expected to give contractors enough access to finish the remaining work and get the facility ready for handover and public use.
The upgraded bus park will feature designated parking and loading bays, sleeping facilities for drivers, modern toilet facilities and landscaped green spaces.
Its design also incorporates collapsible barriers along the perimeter to allow drainage maintenance teams access to the adjoining canal for regular cleaning and maintenance.
Speaking on concerns about possible charges for using the facility, Giwa assured commuters and commercial transport operators that access to the terminal would be free.
He maintained that the facility would remain the property of the Lagos State Government under the supervision of the Ministry of Transportation.
Giwa further explained that the government was working with transport unions to ensure proper management of the facility and prevent unauthorised occupation.
He warned commercial bus drivers against picking up passengers or parking along surrounding road corridors after the terminal becomes operational, adding that the Lagos State Traffic Management Authority would enforce compliance with traffic regulations.
The Obalende project is being developed by MTN Nigeria as part of its corporate social responsibility initiative.
Handed over to MTN by the Lagos State Ministry of the Environment and Water Resources on April 15, 2026, the facility was originally billed for completion by September 11.
That deadline, however, slipped after heavy rainfall between June and August combined with operational challenges from ongoing transport activities at the site.
Work picked up again in October, with construction now advancing on clearing, foundations, pavement, curbing and fencing.
Looking beyond just a bus terminal, the wider redevelopment plan also features electric vehicle charging points, public toilets, recycling facilities, commercial spaces, solar lighting, CCTV installations and tree planting.
With the November inspection and the new December target, the state says it is taking another major step toward turning the once degraded Obalende under bridge area into an organised transport and public use facility.